HARD SHUT-IN PROCEDURE

HARD SHUT-IN PROCEDURE 
WHILE DRILLING ON A FIXED RIG
1. When any indication is observed while drilling that the well may be flowing, stop rotating the drill string, raise the drill string with pumps on until tool joint is above the drill floor.
2. Stop pumps and check for flow, if positive:
3. Close annular or pipe rams.
4. Open choke line HCR valve.
5. Call supervisor and commence plotting a graph of shut in drill pipe pressure. Check pit volume gain.
After the well has been shut in.
In any shut-in procedure it is prudent to line up the annulus to the trip tank above the annular or rams. This will assist in double checking to see if they are leaking. Double check that the well is lined up through the choke manifold prior to circulating kick out.
#Well_Control
#Petroleumguys
Amr Haggag

Comments

Popular posts from this blog

وصفات محسوبة القيمة الغذائية

Deepwater Horizon oil spill - التسرب النفطي في خليج المكسيك 2010

ACCUMULATOR UNIT - koomey Unit (BOP CONTROL UNIT) - وحدة التحكم فى صمامات مانع الانفجار